Ground floor internal and external walls, steel work, and inter floor covering completed before work on the first floor and roof structure gets underway on 17 August.
Ground floor internal and external walls, steel work, and inter floor covering completed before work on the first floor and roof structure gets underway on 17 August.
Brick work completed in readiness for the timber frame, the main components of the ground floor delivered to site in the week commencing 24 July.