The sewer is diverted once the approval for the scheme is received and the rainwater discharge drain is installed across the Recreation Ground. The piling mat is installed but the piling, scheduled for 24 March, is deferred for four weeks as the response to coronavirus begins to bite. The piling company arrive on site xx April and sink over 50 (!) piles in two days. With the piles in place work on the internal drainage is gets underway and the steel works for the concrete pad is put in place.